View project specific information by clicking its location on the map or its name listed below.
Original Construction Cost: $8,200,944
Project Start Date: July 2013
Completion Date: November 2015
Contractor: Woodruff and Sons, Inc.
Improvements on this 1.5 mile project included the construction of a new three-lane road from US 41 to 15th Street East and a new four-lane road from 15th Street East to 19th Street Court East. The contractor also constructed three storm water ponds and formed and poured a triple box culvert to cross Bowless Creek.
SNN News talks with Sia Mollanazar, Manatee County Public Works County Engineer Deputy Director, about the importance of the 44th Ave. extension project.
Original Construction Cost: $11,930,357
Project Start Date: January 2016
Completion Date: January 2018
Contractor: E. T. MacKenzie
Improvements on this 1.62 mile project included new construction of a four-lane roadway on 44th Avenue East through an undeveloped area extending from 19th Street Court East to 30th Street East. This project also included the construction of two single-lane roundabouts. The first roundabout is located at 27th Street East and 38th Avenue East, and the second is located at 30th Street East and 38th Street East.
Additional improvements included sidewalks on the north and south sides of 44th Avenue East; curbs, gutters, lighting, and signalization at 19th Street Court East, US 301, and 30th Street East; water main construction; and drainage and storm water improvements.
Download the project fact sheet.
Original Construction Cost: $10.4 Million
Project Start Date: March 2015
Completion Date: January 2018
Contractor: Woodruff and Sons, Inc.
Improvements on this 1.2 mile project included new construction of a four-lane roadway on 44th Avenue East extending from 30th Street East to 45th Street East, raised medians with grass and concrete curbs, five-foot sidewalks on the north and south sides of 44th Avenue East, four-foot paved bike lanes, and drainage and storm water improvements.
Additional improvements included sidewalks, curbs and gutters, and lighting and signalization at 37th Street and 44th Avenue.
Download the project fact sheet.
Construction Cost: $9.8 Million
Construction Start Date: February 2018
Completion Date: Summer 2020
Contractor: Gator Grading & Paving, LLC
Improvements to this 1.1-mile project included the widening of 45th Street East between SR 70 and 44th Avenue East from a two-lane to a four-lane roadway with grassed raised medians. The bridge deck at Gap Creek was widened to accommodate additional travel lanes. Two pedestrian bridges were constructed to provide pedestrian sidewalks. Access to the existing fire station was improved with an emergency traffic signal. Signalization was also added at the intersection of 44th Avenue East and 45th Street East.